Sunday, July 17, 2016

Plumbing & Heating

During the past 4 weeks the rain has delayed the installation of the vinyl decking however we finally have the upper deck and the front veranda completed.  Exterior doors and windows next week along with the framing inspection.
Plumbing and heating are now completely roughed in  and the inspection is complete.  Fittings for the tubs will be installed prior to insulation.
The siding and soffits are proceeding one wall at a time, but now that the deck surfaces are being completed we can move forward with the siding on the walls adjacent to the deck surfaces.
The brackets to support the swing on the front veranda is also complete.
Electrical and communication wiring are expected to take 2-3 weeks, this wil be done at the same time the exterior is completed.