The crew has been working flat out this week, all perimeter drains were installed for the weeping tile, rain water leaders. The gravel was placed on top of the weeping tile and inside the foundation. The Plumbing crews installed the underground plumbing and and radon gas venting system. Inspections by the City of Kelowna, Horizon Geotechnical and by the Engineering department at AccuTruss were critical this week, a special thanks to the understanding of everyone involved.
Our crew installed the slab seal and the 3" of rigid foam insulation, Scott Plumbing was right on schedule installing all of the hot water loops for floor heating so we made our Friday afternoon pour.