Permits and footings & walls

Although the permitting process was started early on we hit a couple of snags with environmental approvals and and water quality issues, resolution of these items contributed to a 2 day delay in the construction process.  The Building Permit was issued on March 7 2016, footings were inspected and poured on March 8.  The forms for the walls and all reinforcing steel was installed, inspected and poured on March 11.  Damp proofing was done on the weekend, overall we earned back about 3 days in the construction process.